CITY OF SAFFORD FCI SEWER MAIN
JobDetails
| Close Information | Close All Information |
Location: Safford, AZ Owner: City of Safford Began: 08/02/2000, Completed: 04/30/2001
|
 |
|
|
KEMPTON WELL TIE-IN
Job Details
| Close Information | Close All Information |
Location: Safford, Arizona Owner: City of Safford Began: 09/1999, Completed: 08/2000
|
 |
|
|
NEW MODEL CANAL
Job Details
| Close Information | Close All Information |
Location: Hidalgo County, New Mexico Owner: New Model Canal Community & Associates Began: December 1993, Completed: June 1995
|
 |
|
|
CITY OF SAFFORD FCI WATER MAIN
Job Details
| Close Information | Close All Information |
Location: Safford, Arizona Owner: City of Safford Began: June 2001, Completed: April 2002
|
 |
|
|
DUNCAN WATER RENEWAL
Job Details
| Close Information | Close All Information |
Location: Duncan, Arizona Owner: Town of Duncan Began: May 2001, Completed: December 2002
|
 |
|
|
CITY OF WILLCOX WASTEWATER TREATMENT PLANT
Job Details
| Close Information | Close All Information |
Location: Willcox, Arizona Owner: City of Willcox Began: June 2001, Completed: March 2002
|
 |
|
|
CITY OF SAFFORD HILLCREST TRANSMISSION LINE AND WATER STORAGE TANK
JobDetails
| Close Information | Close All Information |
Location: Safford, AZ Owner: City of Safford Began: 11/2008, Completed: 05/2009
|
 |
|
|
CITY OF SAFFORD DISCOVERY TANK AND WATER TRANSMISSION LINE
JobDetails
| Close Information | Close All Information |
Location: Safford, AZ Owner: City of Safford Began: 07/2009, Completed: 06/2010
|
 |
|
|
CITY OF SAFFORD LEBANON TANK AND TRANSMISSION LINE
JobDetails
| Close Information | Close All Information |
Location: Safford, AZ Owner: City of Safford Began: 07/2009, Completed: 06/2010
|
 |
|
|
Greenlee County - Stateline Road Projects
Job Details
| Close Information | Close All Information |
Location: Duncan, AZ Owner: Greenlee County Began: 04/2009, Completed: 07/2009
|